WORKPLAN for project YEAR 2
WORKPLAN for project YEAR 2
Activities | Total duration (number of weeks) | M1 | M2 | M3 | M4 | M5 | M6 | M7 | M8 | M9 | M10 | M11 | M12 | |
Ref.nr/ Sub-ref nr | Title | |||||||||||||
5.6 | 2nd year Project Planning and Co-ordination Report | 1=x | 1=x | |||||||||||
2.3 | First Piloting of Curricula ECTS/ Tuning modular system | 6=x | 2=x | 2=x | 2=x | |||||||||
3.3 | First Round of QA monitoring visits by EU partners with Master-Classes Inputs | 2=x | 2=x | |||||||||||
3.2 | EU & PC QA Evaluation of 1st Piloting | 1=x | 1=x | |||||||||||
5.4 | Interim Project Planning and Coordination QA Meeting | 1=x | 1=x | |||||||||||
2.4 | Second Piloting of Curricula ECTS/ Tuning modular system | 6=x | 2=x | 2=x | 2=x | |||||||||
3.5 | Second round of QA monitoring visits by EU partners | 2=x | 1=x | 1=x | ||||||||||
3.4 | EU & PC QA Evaluation of Second Piloting | 1=x | 1=x | |||||||||||
4.1 | Other dissemination results | 12=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x |
4.3 | ALLVET web-space promotion and maintenance during the 2nd year project running | 12=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x |
4.4 | National PC Conference Awareness Day of 2nd year project running | 1=x | 1=x | |||||||||||
5.5 | Regular Steering Group management meetings to review objectives, monitor progress and ensure QA compliance in Year 2 (on-line) | 12=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x | 1=x |